Guides and explainers

Kodifly's guides explain the circulars, systems and site practices behind Hong Kong public works supervision, one question per page.

Guides and explainers

Start here

  • Digital Works Supervision System (DWSS)

    DEVB TC(W) No. 8/2025 explained

    DEVB TC(W) No. 8/2025 in plain terms. Who must adopt the DWSS, the HK$30 million threshold, 1 April 2026, changes from TC(W) No. 2/2023, cost ceiling, EDMS and audit.

    4 min read

  • Digital Works Supervision System (DWSS)

    How to choose a DWSS

    How to choose a DWSS for Hong Kong public works. Nine criteria from TC(W) No. 8/2025 Annex A, questions to ask any vendor, red flags, and how Kodifly answers each.

    4 min read

  • Smart Site Safety (4S)

    4S and DWSS integration: one hub for site safety data

    How the 4S centralised management platform joins the DWSS Smart Construction Management hub under DEVB TC(W) Nos. 3/2023 and 8/2025, and what flows into it.

    5 min read

Digital Works Supervision System (DWSS)

Digital Works Supervision System (DWSS) for HK$30m+ public works. All six Annex A modules, a 24-hour iCWP API and a tender checklist. Kodifly delivers it complete.

11 guidesExplore DWSS
  • DEVB TC(W) No. 8/2025

    DWSS cleansing inspection checklists module

    What the DWSS Cleansing Inspection Checklists module must do under TC(W) No. 8/2025 Annex A: daily and weekly checklists, records, workflow, statistics and SpatialSense.

    3 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS contract management module: NEC and Health Check data

    What the DWSS Contract Management module must do under TC(W) No. 8/2025 Annex A: compensation events, early warnings, payment, programme, NEC Health Check data.

    4 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS glossary: terms in TC(W) No. 8/2025

    A sourced glossary of DWSS terms in Hong Kong public works: DWSS, iCWP, DSR, RISC, SCM, SDM, EDMS, SSSS or 4S, CSP, NEC and PTE, with the circular paragraph for each.

    4 min readLast updated

  • DEVB TC(W) No. 8/2025

    How to choose a DWSS

    How to choose a DWSS for Hong Kong public works. Nine criteria from TC(W) No. 8/2025 Annex A, questions to ask any vendor, red flags, and how Kodifly answers each.

    4 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS iCWP integration and the iCWP data standard

    How a DWSS feeds DEVB's iCWP under TC(W) No. 8/2025. The data standardisation rule, the 24-hour API clause, what data flows and how SpatialSense meets it.

    4 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS Labour Return module: G.F. 527

    What the DWSS Labour Return module must do under TC(W) No. 8/2025 Annex A: every G.F. 527 field, retrieval from the Site Diary, workflow, statistics and SpatialSense.

    3 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS RISC module: Request for Inspection / Survey Check

    What the DWSS RISC module must do under TC(W) No. 8/2025 Annex A 7.5: form references, fields, workflow and sign-off, dashboard, and how SpatialSense delivers it.

    4 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS Site Diary module: G.F. 536 and Site Record Book

    What the DWSS Site Diary module must do under TC(W) No. 8/2025 Annex A 7.5: G.F. 536, Site Record Book, content, workflow, statistics, and how SpatialSense delivers it.

    3 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS site safety inspection records module

    What the DWSS Site Safety Inspection Records module must do under TC(W) No. 8/2025 Annex A: safety walks, performance records, workflow, statistics and SpatialSense.

    3 min readLast updated

  • DEVB TC(W) No. 8/2025

    DEVB TC(W) No. 8/2025 explained

    DEVB TC(W) No. 8/2025 in plain terms. Who must adopt the DWSS, the HK$30 million threshold, 1 April 2026, changes from TC(W) No. 2/2023, cost ceiling, EDMS and audit.

    4 min readLast updated

  • DEVB TC(W) No. 8/2025

    DWSS tender requirements checklist

    A clause-by-clause checklist of DEVB TC(W) No. 8/2025 Annex A for DWSS tenders: proposal contents, access, security, backup, availability, timeline, handover and AI.

    4 min readLast updated

Co-supervision Platform

DEVB TC(W) 1/2026 Co-supervision Platform (SmartEye) for works above HK$400m. Kodifly supplies the 4D LiDAR, cameras and edge units on about 20 contracts.

Smart Site Safety (4S)

Smart Site Safety System (4S) for HK$30m+ public works, DEVB TC(W) 3/2023, the 4S labelling scheme, and one dashboard for wearables, AI cameras and permits.

Body-worn cameras (BWVC)

DEVB requires body-worn video cameras (BWVC) on public works inspections, announced 24 June 2026. Who wears them, plus Kodifly's 360 helmet camera and dated record.

Not sure which guide applies to your contract?

Tell us the contract and the requirement. We will point you to the clause and show how a dated record meets it.