Skip to content
Kodifly
Book a demo

DEVB TC(W) No. 3/2023, CIC 4SLS

4S Labelling Scheme (4SLS): how a site earns a 4S label

The 4S Labelling Scheme (4SLS) is run by the Construction Industry Council (CIC) with DEVB. It issues a one-year label and plaque to a construction site verified as using a Smart Site Safety System properly. The main contractor applies. Kodifly prepares the layout plans and operating documents and keeps the system working for the inspection.

Last updated

What the label is, and why sites apply

DEVB TC(W) No. 3/2023 requires public works contracts above HK$30 million to adopt a Smart Site Safety System (paragraphs 7 and 8). The circular does not mention a label. The 4S Labelling Scheme came later. DEVB and the CIC launched it in May 2024 to verify that a site really uses 4S and to make that visible (LCQ13, 24 June 2026).

A labelled site displays a 4S plaque with a unique number at its entrances. CIC publishes the labelled project list online and gives it to the Labour Department. Enforcement departments can then look harder at sites without a label. The Labour Department also tells DEVB when a labelled site obviously fails to use 4S properly, and CIC follows up (LCQ13).

The scheme covers public and private works. According to the same LCQ13 reply, about 60 per cent of new construction and maintenance projects above HK$30 million now hold a label.

From application to label

Source for every step is the CIC Application Guide for the 4S Labelling Scheme (March 2025).

  1. Before applying

    Assess the risks

    The safety officer carries out a risk assessment, referring to the Labour Department's Code of Practice on Safety Management. 4S solutions must address the risks found (clauses 3.1 and 3.2).

  2. Main contractor

    Apply online

    Submit the online form, the scope of works, location plans for fixed devices, operation arrangements for devices without a fixed location, and product information (clause 4.1).

  3. Within 1 month

    Site inspection

    CIC reviews the documents and inspects the site. Proper installation and continuous operation must be shown (clauses 3.4 and 4.3).

  4. About 3 months in all

    Result and label

    CIC emails the result. A granted label comes as an electronic copy and a plaque for the site entrances (clauses 4.5 and 5.1).

  5. Every year

    Renew

    The label lasts 1 year. CIC sends a reminder 3 months before expiry, and the renewal is due at least 1 month before expiry (clauses 4.4, 7.1 and 7.2).

What CIC assesses

Four criteria, one for each part of the proof.

CriterionClauseWhat the assessor looks for
Risks identified3.1A safety officer risk assessment based on the scope and nature of the works.
Solutions match the risks3.2Relevant 4S solutions applied to each risk, used broadly across times and locations where applicable.
Evidence of set-up3.3Layout plans for fixed devices, sensors and cameras. Operation arrangements for wearables and other devices without a fixed location.
Working on site3.4Proper installation and continuous functioning shown at the inspection after the expected deployment date.

What Kodifly prepares and runs

The scheme asks for evidence and a working system. We supply both from the same project.

Documents, devices and checks together

  • Risk-based 4S scope from the safety officer's assessment

  • Engineering-level layout plans for fixed devices

  • Operation arrangements for wearables and tags

  • Product information for every device

  • Regular functional checks with kept reports

  • Monthly 4S reports from the platform record

  • Renewal pack with the latest 4S plan

  • Link to DWSS site records

4S Labelling Scheme, answered

What is the 4S Labelling Scheme?

A scheme by DEVB and the CIC, launched in May 2024, that issues labels to construction sites verified as properly adopting 4S (LCQ13 reply, 24 June 2026). A CIC working group approves applications (Application Guide, clause 1.3).

Who can apply for a 4S label?

The main contractor of a local construction project, through its project manager or a delegate (Application Guide, clause 4.1). Public works by ArchSD, CEDD, DSD, EMSD, HyD and WSD and private works are eligible (clause 2.1).

Does DEVB TC(W) No. 3/2023 require a label?

No. The circular requires adoption of a Smart Site Safety System (paragraph 7). The label is the CIC and DEVB scheme that verifies adoption.

How long does it take, and how long does a label last?

The process normally takes about 3 months with the documents in order, and the inspection should be arranged within 1 month of a complete submission (clauses 4.3 and 4.5). A label stays valid for 1 year from approval (clause 4.4).

Do the devices need to be CITF pre-approved?

No. Products without a CITF pre-approved code need product information, such as description, features, specifications and a user guide (clause 4.1.6). Kodifly supplies that documentation with each device.

What happens if a labelled site stops using 4S properly?

CIC may inspect without notice. If 4S is not adopted satisfactorily, the label is confiscated and the CIC website is updated within 7 working days. The contractor may appeal within 7 working days or reclaim the label with an improvement plan and a passed inspection (clauses 8 and 9).

Does the label depend on the recommended packages?

Annex A of the guide recommends 4S packages for sixteen types of work, from a single-tower building to confined space work. A project that departs from the package should give sound reasons (CIC FAQ).

More Smart Site Safety guides

  • 4S and DWSSHow the 4S centralised management platform joins the DWSS Smart Construction Management hub under DEVB TC(W) Nos. 3/2023 and 8/2025, and what flows into it.
  • AI cameraDEVB TC(W) No. 3/2023 clause 5(12)(g): the unsafe scenarios an AI camera must detect, the 80% test and 90% average accuracy, 1 second alarms and video records.
  • Centralised platformWhat DEVB TC(W) No. 3/2023 requires of the 4S centralised management platform (CMP): 30 users, 3 months of data, security, and the alerts every device sends it.
  • 4S componentsThe twelve 4S components in DEVB TC(W) No. 3/2023 Annex A, what each must do, and the rules that apply to every device. Kodifly delivers the set complete.
  • Confined spaceDEVB TC(W) No. 3/2023 clause 5(12)(h): worker counting, PPE checks and oxygen, gas and temperature monitoring for confined spaces under Cap. 59AE.
  • Contract variantsHow 4S requirements vary between Hong Kong contract specifications: 12 or 9 components, 2 or 15 AI cameras, 70 or 100 dB sirens and extra data duties. Kodifly meets both.
  • API and dataHow a 4S platform shares and protects data: API access, OpenAPI v3, single sign-on, SFTP data hub, DWSS links, Tier 3 hosting and data return at the end of the contract.
  • Mobile plant alertDEVB TC(W) No. 3/2023 clause 5(12)(e): 360 degree sensors on excavators and cranes, a 2 m danger zone, 100 dB siren, and the BD mandatory rules for private works.
  • Permit-to-workWhat DEVB TC(W) No. 3/2023 clause 5(12)(c) requires of a digitised permit-to-work system: the high-risk activities, live mobile status and expiry alerts.
  • Plant and tool trackingDEVB TC(W) No. 3/2023 clause 5(12)(b): a unique digital ID on every plant, MEWP, lifting gear and powered tool, with scan checks and overdue alerts.
  • Smart lockDEVB TC(W) No. 3/2023 clause 5(12)(d): electronic locks and keys on electrical cabinets, floor openings, lift shafts and confined spaces, with siren and alerts.
  • Tower crane alertDEVB TC(W) No. 3/2023 clause 5(12)(e): the tower crane loading and unloading danger zone of at least 7 m from the hook, 3 m clearance, 100 dB siren and alerts.
  • VR safety trainingDEVB TC(W) No. 3/2023 clause 6: half-yearly VR safety training for workers in eight high-risk activities, accepted content, hardware and training records.
  • Worker monitoringDEVB TC(W) No. 3/2023 clause 5(12)(f): wearables for every worker with location, standstill, temperature and heart rate alerts, and privacy limits.

Get your site ready for a 4S label

Tell us the contract and the devices on site. We will prepare the layout plans, operating documents and checks for the CIC inspection.