DEVB TC(W) No. 9/2025
Drone progress monitoring for Hong Kong
DEVB TC(W) No. 9/2025 requires qualifying Hong Kong capital works contracts to adopt drone progress monitoring (HECR-4), with 3D photogrammetry models every two weeks. Kodifly flies it, compares the models and passes them into the DWSS.
- Circular
- DEVB TC(W) No. 9/2025
- Applies to
- Capital works contracts above HK$30 million tendered on or after 1 April 2026
- Frequency
- 3D photogrammetry models every two weeks
- Model
- 2 cm resolution, georeferenced, OBJ, over 80% overlap
- Flights
- Cap. 448G, registered with the Civil Aviation Department
- Reports
- Monthly implementation report and a final productivity report
- 7
- of 7 HECR-4 baseline requirements delivered.
- 2
- week cycle for 3D photogrammetry models.
- 2
- cm model resolution, georeferenced.
Every HECR-4 baseline requirement, delivered.
7 of 7 included
Cap. 448G flights, CAD-registered
48MP imagery, 720 panoramas, 4K video, live streaming
2 cm georeferenced 3D models
RTK positioning under 5 cm
Date-by-date progress comparison
Omnidirectional obstacle avoidance
Automatic transfer to the DWSS
See progress between flights.
Open any two dates side by side. The biweekly model lands in the DWSS.

Contractor obligations we cover
Recent Hong Kong public works contract specifications for construction robots add duties beyond the seven baseline requirements. Kodifly takes each one on.
| Obligation | What the contract asks | Kodifly |
|---|---|---|
| Cap. 448G and CAD registration | Comply with the Small Unmanned Aircraft Order (Cap. 448G). Drone and remote pilots registered with the Civil Aviation Department | Meets |
| Insurance and approval programme | Drone insurance meeting Cap. 448G, with sum insured, policy duration and coverage scope, and a programme for any Civil Aviation Department approval | Meets |
| Implementation plan | Submitted one month before deployment: description and performance, management plan and key personnel, validation against the baseline requirements, telecom proposal, hardware and software, location and layout plans with the safe working zone, storage and security, alert follow-up, emergency support and back-up plan. Updated as the site changes | Kodifly drafts it |
| Install, test and demonstrate | On delivery, installed and tested to show the Project Manager it is in good working condition | Meets |
| Uninterrupted operation | Servicing, repair, maintenance, consumables and insurance. An alternative back-up plan for malfunction | Meets |
| Training | Training of all site personnel for the drone | Meets |
| Live streaming | Real-time live streaming as part of the baseline requirements | Meets |
| Site telecom | A site network with the speed, coverage, stability and cybersecurity for real-time data and video. More than one network type, such as Wi-Fi, 4G/5G or broadband, without interference, with power supply | Meets |
| Monthly report | Report at the monthly Site Progress Meeting on setup, operation, malfunction, interruption and modification | Meets |
| Final productivity report | A final report on application and productivity when the works by the drone are complete | Meets |
| Data security | Controls for the confidentiality, integrity and availability of all data, reviewed regularly against prevailing best practice | Meets |
Drone models in the DWSS
TC(W) No. 8/2025
Digital Works Supervision System
Drone models flow into the DWSS record with the six Annex A modules.
Every two weeks, compared and sent.
Two flights two weeks apart are compared zone by zone. The flight streams live, and the results go to the DWSS automatically.
Drone progress monitoring questions
What is HECR-4?
HECR-4 is the drone item in DEVB's Inventory of Highly-Effective Construction Robots under TC(W) No. 9/2025. It covers drones used for progress monitoring, with biweekly submission of 3D photogrammetry models, against seven baseline technical requirements.
Who must adopt drone progress monitoring?
Capital works contracts above HK$30 million tendered on or after 1 April 2026 adopt the robots in DEVB's Inventory (paragraph 8). The drone item applies to all contracts except works that drones cannot view.
What are the seven baseline requirements?
Compliance with Cap. 448G, aerial photography at 48MP with 720 panorama images, 4K fly-through videos and live streaming, 3D photogrammetry models at 2 cm resolution in OBJ format with over 80% overlap, geofencing and RTK positioning better than 5 cm, visual comparison of progress over time, omnidirectional obstacle avoidance, and an internet-accessible, BIM-compatible management system with automatic transfer to the DWSS.
How does the 3D model reach the DWSS?
The Inventory asks for automatic data transfer of the 3D photogrammetry model to the Digital Works Supervision System. SpatialSense passes each model into the DWSS, its own or the department's where one is provided, so it sits with your site records.
Is this the same as fixed-route drone LiDAR for the Co-supervision Platform?
They are related. Drone progress monitoring answers TC(W) No. 9/2025. Fixed-route drone LiDAR is one of two ways to produce the point-cloud video for the Co-supervision Platform under TC(W) No. 1/2026. Kodifly delivers both.
What records must the project office keep?
Project offices measure productivity and keep records (paragraph 13), and the managing department may exempt a contract on exceptional grounds (paragraph 15). On the contractor's side, recent contract specifications ask for a monthly report at the Site Progress Meeting and a final productivity report. Kodifly prepares both.
What goes in the drone implementation plan?
Recent contract specifications ask for it one month before deployment. It covers the drone's performance, the management plan and key personnel, validation against the baseline requirements, the site telecom proposal, hardware and software, location plans with the safe working zone, storage and security, alert follow-up, emergency support with a back-up plan, and the drone insurance and Civil Aviation Department approval programme. Kodifly drafts it.
Who provides the site network for live streaming?
The contractor. Contract specifications ask for a site network that carries real-time data and video reliably, using more than one network type without interference. Kodifly provides the network the drone, live stream and model transfer run on.
Plan your drone capture
Tell us the site, works type and tender date. We will plan the biweekly flights and the DWSS link.