DEVB TC(W) No. 3/2023, Annex A

4S components: what a Smart Site Safety System must include

A Smart Site Safety System (4S) has three parts under DEVB TC(W) No. 3/2023: smart safety devices, a communication network and a centralised management platform (paragraph 5). Annex A lists twelve device components, plus VR safety training. Kodifly supplies, installs and runs the set your site needs as one project.

Last updated

The three parts, and the twelve components

Paragraph 5 of DEVB TC(W) No. 3/2023 says a Smart Site Safety System (SSSS, or 4S) generally has three components. They are smart safety devices that watch high-risk activities, a communication network that carries the data, and a centralised management platform that analyses data, raises alerts and supports follow-up.

Annex A is the sample Particular Specification. Since the memo of 10 July 2026 it lists twelve components in clause 5(12), from the centralised management platform to smart fire and smoke detection, and VR safety training in clause 6. Annex B sets out how each is measured, by the month, and Annex C is the sample Bills of Quantities.

Paragraph 9 lets a project team choose the devices that suit the works. The annexes are a sample, not a minimum and not a limit. Some contract specifications list nine components and leave out MEWP, putlog and fire monitoring, while adding ladders to tracking and permits. The Construction Industry Council groups 4S products into ten main categories for its CITF product list.

The components in Annex A, clauses 5(12) and 6

The core requirement of each, in the circular's own numbers.

ClauseComponentCore requirement
5(12)(a)Centralised management platformReceives, records and displays alerts from every component. At least 30 concurrent users. Data kept for at least 3 months.
5(12)(b)Digitised tracking of plant, MEWPs, lifting appliances, lifting gears and powered toolsA unique digital ID on each item. Scan it to see certification, examination and maintenance records. Alert when overdue. Some contract specifications add ladders.
5(12)(c)Digitised permit-to-workOnline application, issue and tracking. Alert when a permit expires.
5(12)(d)Electronic lock and key access controlLocks on hazardous areas. Siren of at least 70 dB on forced or outdated-key opening.
5(12)(e)Mobile plant danger zone alertSensors for 360 degree cover. Danger zone generally at least 2 m. Siren of at least 100 dB.
5(12)(e)Tower crane lifting zone alertDanger zone generally at least 7 m radius from the hook. Siren of at least 100 dB.
5(12)(f)Smart monitoring of workersIndoor and outdoor location, standstill alert, body temperature and heart rate alerts. Vital sign values are not shown on the platform.
5(12)(g)AI safety monitoringAt least 80% true positive in the live test and 90% on average after four weeks. Alarm within 1 second.
5(12)(h)Confined space monitoringWorker counting and tracking, and gas, oxygen and temperature readings with real-time alerts.
5(12)(i)MEWP smart monitoringProximity sensors. Siren of at least 70 dB and automatic stop inside the set distance (500 mm in the sample).
5(12)(j)Scaffolding putlog monitoringWarning within 30 seconds of a wire-cut. Tension measured every 60 seconds.
5(12)(k)Smart fire and smoke detectionAlert within 30 seconds of an abnormality. Video from 1 minute before to 1 minute after.
6VR safety trainingHalf-yearly training for workers in eight named high-risk activities.

MEWP, putlog and fire: the three components added in July 2026

The memo of 10 July 2026 added clauses 5(12)(i) to (k). Each sends its alerts to the platform, and Kodifly supplies, fits and runs all three.

  1. MEWP smart monitoring, 5(12)(i)

    • A secondary guarding device on every MEWP on site, to protect the operator from entrapment. It may be built in by the maker or fitted afterwards.
    • Proximity, anti-collision or pressure sensors that detect obstacles around and above the platform.
    • Inside 500 mm, or the distance the Safety Officer sets, a continuous siren of at least 70 dB and/or a flashing red light, and an automatic stop of the MEWP.
    • No obstacle to rescue. Operators, workers and rescuers are briefed, and the system is a pre-operation check item.
    • A register in the tracking system of every MEWP and whether it is fitted, included in the monthly safety report.
  2. Scaffolding putlog monitoring, 5(12)(j)

    • Designated tie-wires or putlogs watched by a sensing wire circuit, tilt sensor or similar.
    • A warning within 30 seconds of a wire-cut or damage to a putlog.
    • Tension measured every 60 seconds, or a longer agreed interval, with a warning above the agreed threshold.
    • A siren of at least 70 dB and/or a flashing red light at the scene.
    • Sensors in protective casings, with a warning when a battery falls below 10%.
    • Sensor quantities and locations accepted by the Project Manager. No interference with, or damage to, the scaffold.
  3. Smart fire and smoke detection, 5(12)(k)

    • Cover of the areas the Safety Officer names by risk assessment, such as dangerous goods stores, flammable material stores and battery charging areas.
    • AI-capable IP cameras, thermal imaging cameras, thermal sensors or a mix, in protective casings. The AI cameras can be part of the AI safety monitoring system.
    • A siren of at least 70 dB and/or a flashing red light within 30 seconds of visible flame, smoke or a set temperature threshold.
    • An alert to supervisors and the Safety Officer with the date, time and location.
    • Encrypted video from 1 minute before to 1 minute after the abnormality.

Rules that apply to every component

These sit outside the individual device clauses. Each one is a point an auditor can check.

  1. Set up

    • Submit the implementation plan within 14 days of the starting date or tender acceptance (clause 2(1)).
    • Deliver every component within 1 month of the plan being accepted, unless agreed otherwise (clause 2(3)).
    • Install and test within 5 working days of delivery (clause 2(5)).
    • Provide a site network that supports mobile communication, and use more than one network system where needed (clause 4).
  2. Every alert

    • Reach at least 90% accuracy in detecting alert scenarios, proved by a live trial (clause 5(2)).
    • Send each alert to the platform with person or machine ID, date, time and duration (clause 5(2)).
    • Timestamp and encrypt data, make it available by API and stream it to the platform (clause 5(6)).
    • Use cameras with protective casing, at least 1080 pixels and 5x optical zoom (clause 5(3)).
  3. Every day and every month

    • Check devices before work each day and record any irregularity (clause 5(8)).
    • Keep an action plan with response times and named supervisors (clause 5(9)).
    • Repair or replace within 24 hours of a reported fault (clause 5(5)).
    • Report monthly to the Site Safety Management Committee (clause 5(11)).
    • Hold 99.9% uptime in working hours and comply with the Personal Data (Privacy) Ordinance (clauses 1(2) and 1(3)).

How Kodifly delivers the set

One project, one team, one platform. We specify the components your risk assessment calls for, then supply, install and run them.

Software, devices and installation together

  • Platform and permit-to-work in SpatialSense

  • Electronic locks for hazardous areas

  • Plant and tool tracking

  • Mobile plant and tower crane alerts

  • Wearables for workers

  • AI cameras

  • Confined space monitoring

  • MEWP, putlog and fire detection

  • Monthly 4S report from the platform record

  • Link to the DWSS hub

4S components, answered

What are the components of a Smart Site Safety System?

Three parts under paragraph 5 of DEVB TC(W) No. 3/2023: smart safety devices for high-risk activities, a communication network for the data, and a centralised management platform for analysis, alerts and follow-up. Annex A, clause 5(12), lists twelve device components.

How many 4S components does Annex A list?

Twelve in clause 5(12), plus VR safety training in clause 6. The memo of 10 July 2026 added smart monitoring for MEWPs, smart monitoring for scaffolding putlogs, and smart fire and smoke detection.

What does the MEWP component do?

It guards the MEWP operator against entrapment. Sensors detect obstacles around and above the platform, and inside 500 mm, or the distance the Safety Officer sets, a siren of at least 70 dB sounds and the MEWP stops automatically (clause 5(12)(i)).

Must a contract use every component?

No. Project teams select suitable devices for the nature of the works and the high-risk activities involved, and are not limited to the annexes (paragraph 9).

What accuracy must a 4S alert reach?

Any component that issues automated warnings must reach at least 90% accuracy in detecting its scenarios, proved by a live trial (clause 5(2)). AI safety monitoring must also pass a test of at least 80% true positive and then average 90% (clause 5(12)(g)).

What does 4S cost?

The estimated cost would normally not exceed HK$10 million or 1% of the estimated contract sum, whichever is lower (paragraph 10). The contractor bears servicing, repair and consumables (clause 3(1)).

More Smart Site Safety guides

  • 4S and DWSSHow the 4S centralised management platform joins the DWSS Smart Construction Management hub under DEVB TC(W) Nos. 3/2023 and 8/2025, and what flows into it.
  • AI cameraDEVB TC(W) No. 3/2023 clause 5(12)(g): the unsafe scenarios an AI camera must detect, the 80% test and 90% average accuracy, 1 second alarms and video records.
  • Centralised platformWhat DEVB TC(W) No. 3/2023 requires of the 4S centralised management platform (CMP): 30 users, 3 months of data, security, and the alerts every device sends it.
  • Confined spaceDEVB TC(W) No. 3/2023 clause 5(12)(h): worker counting, PPE checks and oxygen, gas and temperature monitoring for confined spaces under Cap. 59AE.
  • Contract variantsHow 4S requirements vary between Hong Kong contract specifications: 12 or 9 components, 2 or 15 AI cameras, 70 or 100 dB sirens and extra data duties. Kodifly meets both.
  • API and dataHow a 4S platform shares and protects data: API access, OpenAPI v3, single sign-on, SFTP data hub, DWSS links, Tier 3 hosting and data return at the end of the contract.
  • 4S Labelling SchemeGetting a 4S label, step by step: the main contractor applies, CIC inspects the site, and the process takes about 3 months. One-year validity, renewal and confiscation.
  • Mobile plant alertDEVB TC(W) No. 3/2023 clause 5(12)(e): 360 degree sensors on excavators and cranes, a 2 m danger zone, 100 dB siren, and the BD mandatory rules for private works.
  • Permit-to-workWhat DEVB TC(W) No. 3/2023 clause 5(12)(c) requires of a digitised permit-to-work system: the high-risk activities, live mobile status and expiry alerts.
  • Plant and tool trackingDEVB TC(W) No. 3/2023 clause 5(12)(b): a unique digital ID on every plant, MEWP, lifting gear and powered tool, with scan checks and overdue alerts.
  • Smart lockDEVB TC(W) No. 3/2023 clause 5(12)(d): electronic locks and keys on electrical cabinets, floor openings, lift shafts and confined spaces, with siren and alerts.
  • Tower crane alertDEVB TC(W) No. 3/2023 clause 5(12)(e): the tower crane loading and unloading danger zone of at least 7 m from the hook, 3 m clearance, 100 dB siren and alerts.
  • VR safety trainingDEVB TC(W) No. 3/2023 clause 6: half-yearly VR safety training for workers in eight high-risk activities, accepted content, hardware and training records.
  • Worker monitoringDEVB TC(W) No. 3/2023 clause 5(12)(f): wearables for every worker with location, standstill, temperature and heart rate alerts, and privacy limits.

Plan the 4S set for your site

Send us the risk assessment and the contract clauses. We will return the components, quantities and layout your site needs.