Buildings Department measure, planned by January 2027

Rebar inspection records: every element on record before the concrete goes in

A rebar inspection record is the dated photo or video that shows the steel reinforcement of a structural element before it is concreted. Hong Kong's Buildings Department (BD) plans to require one in or before January 2027. Contractors record the rebar in the structural elements inspected, technically competent persons under the project's registered structural engineer verify every record, and all records go to BD for spot checks (LCQ1, 11 November 2026). SpatialSense by Kodifly pins each record to the plan with its date, time and inspection sign-off.

What
Photographs or videos of the rebar in the structural elements inspected, before concreting
Who records
The contractor
Who verifies
Technically competent persons under the project's registered structural engineer, every record
Who receives
The Buildings Department, all records, for spot checks
After concreting
An accredited laboratory audit-checks the rebar; the engineer reviews the report
When
In or before January 2027. BD is consulting the industry on the details

BD has not yet published the implementation details. This page states what the Secretary for Development told the Legislative Council on 11 November 2026, and it will be updated when BD issues its requirements.

What the Buildings Department plans to require

The enhanced measures in the Secretary for Development's reply, part (1). They follow BD's doubling of audit checks on rebar before and after concreting in May 2025.

StageWhoWhat
Before concretingContractorTakes photographs or videos that record the arrangement of steel reinforcement in the structural elements inspected
Before concretingTechnically competent persons under the project's registered structural engineerVerify all of the records
Before concretingBuildings DepartmentReceives all the photo and video records and spot-checks them
After concretingContractorEngages an accredited laboratory to carry out audit checks on the steel reinforcement
After concretingRegistered structural engineer, then BDThe engineer reviews the laboratory report, and it is submitted to BD for spot checks

Source: LCQ1, 11 November 2026, reply part (1). BD is consulting the industry on the implementation details and plans to implement the measures in or before January 2027.

What a checkable rebar record needs, in one system.

10 of 10 included

  • Photo, video or 360 capture of each element

  • Pinned to the plan by level and grid

  • Date, time and capture ID on every record

  • Linked to the inspection request

  • Inspection sign-off kept with the record

  • AI tags rebar mats, sleeves and bar chairs

  • Close-up photos and measurements

  • The same view, before and after the pour

  • Viewer access and reports for the engineer

  • Secure records and audit trail

Record

Before it is covered, it is on record.

The engineer walks the bay with a 360 camera or takes photos on a phone. SpatialSense places each capture on the plan with its date, time and capture ID, and saves it against the inspection that passed the works. After the pour, the same view still shows what is inside.

  • Level, grid and element on every record
  • Linked to the inspection request and the site diary
  • Compare the same spot before and after the pour

See SpatialSense

A hard hat with a 360 camera mounted on top, used to capture a site walk

The record is dated supporting evidence. It does not replace the inspection itself or the engineer's judgement.

From fixed steel to a record that can be spot-checked.

  1. Fix and request

    The contractor fixes the steel and raises the inspection request for the element.

  2. Record

    Photos or a 360 walk of the element, placed on the plan by level and grid.

  3. Verify

    The engineer's site staff check the record against the approved plans and sign it off.

  4. Submit

    Every record for the pour is ready to hand over, in order.

  5. After the pour

    The laboratory's audit report can be filed against the same element.

Be ready before the measure starts

Book a demo

Verify

The inspection and the record stay together.

Each inspection request moves through Submitted, Inspected and Approved, with the person and the time at each step. The photos sit on the request. When someone asks what was checked on Level 5, bay E to F, the answer is one record.

Inspection requests in SpatialSense

Which record rule applies to which site

Hong Kong now has three separate rules on inspection records. Two are for public works contracts. The third comes from the Buildings Department.

RuleApplies toWhat it asks forStatus
Digital Works Supervision System, DEVB TC(W) No. 8/2025Capital works contracts above HK$30 millionWorks inspection and survey procedures run digitally, including inspection requests and the site diaryTendered on or after 1 April 2026
Body-worn video cameras, DEVBAll public works contractsResident site staff and contractors' frontline staff are equipped with cameras during site inspectionsSince June 2026
Rebar photo and video records, Buildings DepartmentBuilding works that BD regulatesA photo or video record of rebar before concreting, verified by technically competent persons, with all records submitted to BDPlanned in or before January 2027

The first two rules are the technology measures the Secretary for Development named for public works in the same reply, part (2).

Rebar record guides

  • Requirement explained

    BD plans to require photo or video records of rebar before concreting in Hong Kong, by January 2027. Who records, who verifies, what goes to BD and what is still open.

  • Public and private works

    Does DWSS apply to private projects in Hong Kong? DWSS and body-worn cameras are for public works. The Buildings Department's rebar record measure is separate.

  • What to record

    A checklist for the photo or video record of rebar before concreting. What each record should show so it can be verified against the approved plans and spot-checked.

Rebar inspection record questions

What is a rebar inspection record?

It is the dated photo or video that shows the steel reinforcement of a structural element before it is concreted. It lets someone who was not on site see the arrangement of the bars after the concrete has covered them.

Is a photo or video record of rebar required in Hong Kong?

It will be. The Secretary for Development told the Legislative Council on 11 November 2026 that, before concrete casting, contractors will be required to take photographs or videos to record the arrangement of steel reinforcement in the structural elements inspected. The Buildings Department plans to implement the measure in or before January 2027.

Who checks the records?

Technically competent persons under the project's registered structural engineer verify all of them. All records are then submitted to the Buildings Department, which spot-checks them (LCQ1, 11 November 2026, reply part (1)).

What happens after the concrete is poured?

The contractor engages an accredited laboratory to carry out audit checks on the steel reinforcement. The project's registered structural engineer reviews the report, and it is submitted to the Buildings Department for spot checks.

Has the Buildings Department published the details?

Not yet. The reply says BD is consulting the industry on the implementation details. Matters such as the file format, what each record must show and how records are submitted are for BD to set. This page will be updated when it does.

Is a 360 camera required?

No. The reply says photographs or videos. A 360 walk is a video record that shows the whole element and what is around it in one pass, and close-up photos can be added where bar size and spacing need to be read.

Does the record replace the inspection?

No. The technically competent persons still inspect the works and verify the record. The record is what lets the engineer and the Buildings Department check afterwards what was inspected.

What does SpatialSense add to photos on a phone?

Every capture is placed on the plan by level and grid, carries its date, time and capture ID, and is linked to the inspection request with its sign-off. The records for a pour can be found and handed over as one set, not searched for across phones and chat groups.

Be ready before the measure starts

Tell us the project and the pour programme. We will show the record on a site like yours, from the first photo to the signed-off set.