DEVB TC(W) No. 8/2025, Annex A 7.5.1(i)
DWSS RISC module: Request for Inspection / Survey Check
The RISC module is the first of six mandatory DWSS modules in DEVB TC(W) No. 8/2025 (Annex A 1.2.1 and 7.5.1(i)). It digitises the Request for Inspection of Works form, follows the approved Inspection and Test Plan, keeps every resubmission linked, and reports status on a dashboard. Kodifly delivers it in SpatialSense.
Last updated
What the RISC module is
Annex A 7.5.1(i) points the RISC form to Appendix 7.82A (GCC) and Appendix 7.82B (NEC) of the Project Administration Handbook 2024, "Request for Inspection of Works". ArchSD contracts use Form D/COW.006 for COW and Form D/BSI.006 for BSI, or another relevant form for the same purpose.
Submission and approval must also follow the approved Inspection and Test Plan of the relevant works activity. The requesting officer can submit and resubmit until the inspection is certified completed, and the linkage of inspection history and resubmissions must be recorded for search and retrieval.
Fields, records and rules
| Item | What Annex A requires | Clause |
|---|---|---|
| Form reference | PAH 2024 Appendix 7.82A (GCC) or 7.82B (NEC), or ArchSD form | 7.5.1(i)(a) |
| Record identifier | Module, type, six-digit serial and revision, for example RISC/SUR/000001A. Types include SUR (survey) and SI (site inspection) | 7.3.3, 7.3.4 |
| Photographs | Photo records in the form, taken by the same device, with date, time and GPS stored | 7.5.1(i)(e), 7.4.7, 7.4.9 |
| Photo size | Compressed automatically, under 1 MB each or as agreed | 7.4.8 |
| Locked records | Submitted forms cannot be edited. Changes go through rejection and resubmission | 7.3.7, 7.4.2 |
| Time stamp | Every submission and approval time-stamped with issuer or approver | 7.3.8 |
| Process time | User assignment and time stamp recorded along the workflow | 7.4.6 |
| Overdue alerts | Email or push alerts for overdue actions and irregularities | 7.4.3 |
Workflow and who signs
Annex A sets the stages. The workflow is agreed with the employer's representative within six weeks, and the forms are set up within three months (7.4.4). That agreement names the people.
Draft and submit
The requesting officer drafts on the app or browser (7.3.6), then assigns the form to the next reviewing party (7.4.1).
Review or reject
The assigned party approves, rejects or responds on the app or browser (7.4.5). Each action is time-stamped.
Resubmit with history
A rejected request is resubmitted as a new revision, linked to the earlier ones (7.3.7, 7.5.1(i)(d)).
Certified complete
The request closes when the inspection is certified completed (7.5.1(i)(c)).
Inspection status dashboard
Annex A 7.5.1(i)(f) lists what the RISC summary must show. The DSR adds the iCWP measures.
| Annex A dashboard item | Example iCWP measure (DSR 4.3) |
|---|---|
| Overdue actions | Number of overdue RISC forms in a period |
| Completed, incomplete and outstanding inspections | Number completed, incomplete and outstanding in a period |
| Passing and failing rate | Passing and failure statistics, and first-inspection failure rate |
| Process time analytics | Average elapsed time, and total delayed approvals |
How SpatialSense does it
SpatialSense is built to Annex A 7.5.1(i), and Kodifly delivers it as part of the complete DWSS.
Built to Annex A
RISC with linked resubmission history
Photos dated and placed on the plan
360 capture linked to the request
Status dashboard
Web, iOS and Android apps
Data to iCWP
Submitted, inspected, approved, on the clock.
Each step is time-stamped in the audit trail. The allowable time and the time remaining show on the request, so the approver acts before it lapses.
RISC module, answered
What does RISC stand for?
Request for Inspection / Survey Check. It is the first of the six mandatory DWSS modules (Annex A 1.2.1 and 7.5.1(i)).
Which form does the RISC module replace?
It digitises the Request for Inspection of Works form in the Project Administration Handbook 2024, Appendix 7.82A for GCC and 7.82B for NEC. ArchSD contracts use D/COW.006 or D/BSI.006.
Can a submitted RISC form be edited?
No. Submitted, reviewed or approved records are locked. Changes happen only through rejection and resubmission, which supersedes the earlier record (7.3.7 and 7.4.2).
Do photos have to come from the same device?
Yes. Only photos captured by the same device can be inserted into DWSS forms and records, and date, time and GPS location are stored with them (7.4.7 and 7.4.9). GPS can be exported to HK80 coordinates.
What data does RISC send to iCWP?
DSR section 4.3 lists non-conformance and urgent counts, average elapsed time, revisions, overdue forms, completion status, passing and failure statistics, delayed approvals, first-inspection failure rate and raw data.
Who approves a RISC form?
Annex A does not name signatories. The workflow agreed with the employer's representative within six weeks sets who reviews and certifies, and each approval is time-stamped with the approver (7.4.4 and 7.3.8).
Related guides
More DWSS guides
- Cleansing inspectionWhat the DWSS Cleansing Inspection Checklists module must do under TC(W) No. 8/2025 Annex A: daily and weekly checklists, records, workflow, statistics and SpatialSense.
- Contract managementWhat the DWSS Contract Management module must do under TC(W) No. 8/2025 Annex A: compensation events, early warnings, payment, programme, NEC Health Check data.
- GlossaryA sourced glossary of DWSS terms in Hong Kong public works: DWSS, iCWP, DSR, RISC, SCM, SDM, EDMS, SSSS or 4S, CSP, NEC and PTE, with the circular paragraph for each.
- How to chooseHow to choose a DWSS for Hong Kong public works. Nine criteria from TC(W) No. 8/2025 Annex A, questions to ask any vendor, red flags, and how Kodifly answers each.
- iCWP data standardHow a DWSS feeds DEVB's iCWP under TC(W) No. 8/2025. The data standardisation rule, the 24-hour API clause, what data flows and how SpatialSense meets it.
- Labour ReturnWhat the DWSS Labour Return module must do under TC(W) No. 8/2025 Annex A: every G.F. 527 field, retrieval from the Site Diary, workflow, statistics and SpatialSense.
- Site DiaryWhat the DWSS Site Diary module must do under TC(W) No. 8/2025 Annex A 7.5: G.F. 536, Site Record Book, content, workflow, statistics, and how SpatialSense delivers it.
- Site safety inspectionWhat the DWSS Site Safety Inspection Records module must do under TC(W) No. 8/2025 Annex A: safety walks, performance records, workflow, statistics and SpatialSense.
- Smart construction managementSmart construction management in the DWSS under TC(W) No. 8/2025: the SCM hub, alerts, dashboards, iCWP data within 24 hours, the AI tool, and how SpatialSense meets it.
- TC(W) No. 8/2025DEVB TC(W) No. 8/2025 in plain terms. Who must adopt the DWSS, the HK$30 million threshold, 1 April 2026, changes from TC(W) No. 2/2023, cost ceiling, EDMS and audit.
- Tender checklistA clause-by-clause checklist of DEVB TC(W) No. 8/2025 Annex A for DWSS tenders: proposal contents, access, security, backup, availability, timeline, handover and AI.
See RISC running on your contract form
Send us the contract type and your Inspection and Test Plan. We will show the workflow in SpatialSense.