DEVB TC(W) No. 8/2025
DWSS glossary: terms in TC(W) No. 8/2025
This glossary defines the terms used in DEVB TC(W) No. 8/2025 and its Annex A, including DWSS, iCWP, RISC, SDM, EDMS and NEC. Each entry cites the paragraph or annex clause it comes from. Where a term comes from a related DEVB document, the entry names it.
Last updated
How to read this glossary
The circular and Annex A use full names in most places. Short forms such as SCM are used in this guide for brevity. The circular prevails over any definition here, and each row cites where the wording comes from.
DWSS terms
| Term | Full name | Meaning | Source |
|---|---|---|---|
| DWSS | Digital Works Supervision System | A centralised construction management platform for submission and approval workflows, contract management, supervision and monitoring. It is also the platform for smart site applications. | Annex A 1.1.1, para 9 |
| iCWP | Integrated Capital Works Platform | DEVB's platform, developed in phases, that collects and consolidates data from the DWSS and other digital systems. | Para 17 |
| DSR | Data Standardisation Report for DWSS | The DEVB living document that sets the datasets sent from the DWSS to iCWP. Version 1.2 is dated December 2025. | Para 17, DSR |
| RISC | Request for Inspection/Survey Check | The first of the six mandatory modules. | Annex A 1.2.1 |
| SCM | Smart Construction Management | The data hub that collects and consolidates data from smart site applications such as IoT devices, remote sensors, AI applications and smart carry-on devices. | Annex A 1.3.1 |
| SDM | Smart Document Management | A web-based, workflow-enabled component for formal project documents such as correspondence, submissions, drawings and reports. | Annex A 1.4.1 |
| EDMS | Electronic Document Management System | A separate system contractors no longer have to procure, because SDM fulfils the requirement. | Paras 6(a), 11 |
| SSSS or 4S | Smart Site Safety System | DEVB circulars write SSSS. Kodifly's guides write 4S. Where both apply, the SSSS central platform is merged into the SCM hub. | Para 7 footnote 1 |
| CSP | Co-supervision Platform | DEVB's SmartEye platform for remote supervision, set out in TC(W) No. 1/2026. It connects to the SCM hub through an API or other means. | TC(W) No. 1/2026 |
| NEC | New Engineering Contract | A contract form that the Contract Management module supports. The DSR lists NEC3, NEC4 and the NEC Hong Kong Edition. | Annex A 7.5.1(vi)(a), DSR 2.7.1 |
| PTE | Pre-tender estimate | The estimate that sets the HK$30 million threshold and the cost ceiling. The circular writes the term in full. | Paras 1, 8, 12 |
| Employer's representative | The Architect, the Engineer, the Supervising Officer, the Project Manager or the like | The person who reviews the DWSS proposal and appoints the project team member. | Para 13, footnote 3 |
| RSS | Resident site staff | Appointed to manage the DWSS on site, at professional rank, or at inspectorate rank where justified and supported by the professional-rank project team member. | Annex A 3.2.2 |
| MDM | Mobile device management | Software to distribute, upgrade, manage and wipe DWSS apps and data on registered mobile devices. | Annex A 5.6.1 |
| RPO | Recovery Point Objective | The most data loss allowed after a failure. The Annex sets it at not more than 24 hours. | Annex A 2.4.6 |
| CE, PMI, EW | Compensation Event, Project Manager's Instruction, Early Warning | The contract workflows in the Contract Management module. | Annex A 7.5.1(vi) |
Where each term shows up in SpatialSense
Kodifly delivers the whole DWSS as one project, built to Annex A.
Built to Annex A
Workflow Management modules
Smart Construction Management hub
Smart Document Management
API to iCWP
Web, iOS and Android apps
DWSS terms, answered
What does DWSS stand for?
Digital Works Supervision System. DEVB requires it on capital works contracts with a pre-tender estimate above HK$30 million tendered on or after 1 April 2026 (paragraphs 1 and 8).
What is the difference between SCM and SDM?
Smart Construction Management is the data hub for smart site applications. Smart Document Management is the component for formal project documents. Both sit beside Workflow Management (paragraph 7).
Is 4S the same as SSSS?
Yes. DEVB circulars write SSSS for the Smart Site Safety System, and Kodifly's guides write 4S. With a DWSS, the SSSS central platform joins the SCM hub (paragraph 7, footnote 1).
What is the DSR and where is it published?
The Data Standardisation Report for DWSS is published on the DEVB website. The circular calls it a living document that DEVB updates (paragraph 17, Annex A 11.1.5).
Who is the employer's representative?
The Architect, the Engineer, the Supervising Officer, the Project Manager or the like, as defined under the contract (paragraph 13, footnote 3).
Related guides
More DWSS guides
- Cleansing inspectionWhat the DWSS Cleansing Inspection Checklists module must do under TC(W) No. 8/2025 Annex A: daily and weekly checklists, records, workflow, statistics and SpatialSense.
- Contract managementWhat the DWSS Contract Management module must do under TC(W) No. 8/2025 Annex A: compensation events, early warnings, payment, programme, NEC Health Check data.
- How to chooseHow to choose a DWSS for Hong Kong public works. Nine criteria from TC(W) No. 8/2025 Annex A, questions to ask any vendor, red flags, and how Kodifly answers each.
- iCWP data standardHow a DWSS feeds DEVB's iCWP under TC(W) No. 8/2025. The data standardisation rule, the 24-hour API clause, what data flows and how SpatialSense meets it.
- Labour ReturnWhat the DWSS Labour Return module must do under TC(W) No. 8/2025 Annex A: every G.F. 527 field, retrieval from the Site Diary, workflow, statistics and SpatialSense.
- RISCThe RISC form in the DWSS under TC(W) No. 8/2025 Annex A 7.5: the form it digitises, fields, workflow and sign-off, dashboard, and how SpatialSense delivers it.
- Site DiaryWhat the DWSS Site Diary module must do under TC(W) No. 8/2025 Annex A 7.5: G.F. 536, Site Record Book, content, workflow, statistics, and how SpatialSense delivers it.
- Site safety inspectionWhat the DWSS Site Safety Inspection Records module must do under TC(W) No. 8/2025 Annex A: safety walks, performance records, workflow, statistics and SpatialSense.
- Smart construction managementSmart construction management in the DWSS under TC(W) No. 8/2025: the SCM hub, alerts, dashboards, iCWP data within 24 hours, the AI tool, and how SpatialSense meets it.
- TC(W) No. 8/2025DEVB TC(W) No. 8/2025 in plain terms. Who must adopt the DWSS, the HK$30 million threshold, 1 April 2026, changes from TC(W) No. 2/2023, cost ceiling, EDMS and audit.
- Tender checklistA clause-by-clause checklist of DEVB TC(W) No. 8/2025 Annex A for DWSS tenders: proposal contents, access, security, backup, availability, timeline, handover and AI.
Ask about a term on your contract
Send us the clause or the term. We will show where it sits in SpatialSense.