DEVB TC(W) No. 8/2025, Annex A 7.5.1(vi)
DWSS contract management module: NEC and Health Check data
The Contract Management module is the sixth mandatory DWSS module in DEVB TC(W) No. 8/2025 (Annex A 7.5.1(vi)). It runs compensation events, Project Manager's Instructions, early warnings, programme and payment workflows, and since this circular must hold NEC Health Check data. Kodifly delivers it in SpatialSense.
Last updated
What the module is
Annex A 7.5.1(vi)(a) says Contract Management covers workflow processes such as Compensation Event, Project Manager's Instruction, Early Warning, programme and payment, as set out in the contract documents and the matching contract forms such as the New Engineering Contract (NEC). The payment workflow must follow the corresponding Payment Certificate.
Paragraph 6(b) of the circular enhances the module to include Health Check data for NEC projects, for proactive monitoring of contract performance and risk management. In the DWSS filing format the records use the type code CM, with sub-types PMI, CE, EW and IP (interim payment) (7.3.4).
Fields by workflow
Annex A 7.5.1(vi)(c) sets the contents of each workflow.
| Workflow | Fields Annex A requires |
|---|---|
| Compensation Event, Project Manager's Instruction, Early Warning | Title and reference number, description, justification, dates (submission, response, implementation, closing), cost and time implication, supporting documents |
| Payment | Financial data in Payment Certificates, interim assessment of the Contractor's share (NEC Option C and D), supporting documents |
| Programme | Contract Key Dates and Completion Dates, planned Key Dates and Completion Dates, supporting documents |
| Key contract information | Contract number, title and scope. Financial data such as Approved Contract Sum, Price for Work Done to Date and Fee Percentage. Key dates. NEC Health Check data |
Workflow and who signs
Annex A does not name signatories. The NEC roles appear in the DSR measures, and the workflow agreed with the employer's representative sets the route (7.4.4).
Notify or warn
The Contractor or the Project Manager raises an early warning or notifies a compensation event. The DSR counts each by initiator.
Respond and quote
The Project Manager accepts or rejects a notified event and instructs a quotation. The DSR tracks quotation submission and assessment times.
Implement or close
The event is implemented with its cost and time effect, or closed. Dates are held for each stage (7.5.1(vi)(c)).
Pay and update
Payment follows the Payment Certificate workflow. Key financial and date data update through the workflow (7.5.1(vi)(b), (d)).
NEC Health Check data in the DSR
DSR version 1.2 (December 2025) adds NEC Health Check data. It has six parts, G1 to G6.
| Part | What it holds |
|---|---|
| G1 Contract general information | Department and division, contract details and personnel, NEC version and options, contractor and consultant |
| G2 Financial performance | Tender and contract prices, price variations, pain and gain share, expenditure percentages, compensation event cost impacts |
| G3 Time performance | Contract duration and time elapsed, completion dates, sectional completion, key dates, extension of time |
| G4 Programme management | Programme submission and acceptance, revision intervals, processing times |
| G5 Early warnings | Totals by source, closure rates, age of open warnings, resolution times |
| G6 Compensation events | Notification, implementation rates, processing timelines, cost and time implications, age of pending events |
How SpatialSense does it
SpatialSense is built to Annex A 7.5.1(vi), and Kodifly delivers it as part of the complete DWSS.
Built to Annex A
Compensation event and PMI workflow
Early warning workflow
Payment and programme workflow
NEC Health Check data
Contract statistics dashboard
Data to iCWP
From early warning to compensation event.
An NEC early warning keeps its history: raised, discussed at the risk reduction meeting, then notified as a compensation event. Health Check data sits beside it.
Contract Management module, answered
What does the Contract Management module cover?
Compensation Events, Project Manager's Instructions, Early Warnings, programme and payment workflows, as set out in the contract documents and forms such as NEC (Annex A 7.5.1(vi)(a)).
What is new for NEC contracts?
Paragraph 6(b) adds Health Check data for NEC projects, and Annex A 7.5.1(vi)(d)(iv) lists NEC Health Check data among the key contract information the module must hold and update through workflow.
Does it handle payment?
Yes. The workflow stated in the corresponding Payment Certificate must be incorporated, including the interim assessment of the Contractor's share under NEC Option C and D (7.5.1(vi)(b) and (c)).
What statistics must it show?
Compensation Events, Project Manager's Instructions, Early Warnings, updated financial status, Completion Dates and NEC Health Check data (7.5.1(vi)(e)).
Which contract forms does iCWP expect?
The DSR basic information lists the contract form as GCC, NEC3, NEC4 or the NEC Hong Kong Edition, with the main options.
Is the programme file sent to iCWP?
The DSR collects the raw project programme file, such as a Primavera or Microsoft Project file, for big data analytics purposes only.
Related guides
More DWSS guides
- Cleansing inspectionWhat the DWSS Cleansing Inspection Checklists module must do under TC(W) No. 8/2025 Annex A: daily and weekly checklists, records, workflow, statistics and SpatialSense.
- GlossaryA sourced glossary of DWSS terms in Hong Kong public works: DWSS, iCWP, DSR, RISC, SCM, SDM, EDMS, SSSS or 4S, CSP, NEC and PTE, with the circular paragraph for each.
- How to chooseHow to choose a DWSS for Hong Kong public works. Nine criteria from TC(W) No. 8/2025 Annex A, questions to ask any vendor, red flags, and how Kodifly answers each.
- iCWP data standardHow a DWSS feeds DEVB's iCWP under TC(W) No. 8/2025. The data standardisation rule, the 24-hour API clause, what data flows and how SpatialSense meets it.
- Labour ReturnWhat the DWSS Labour Return module must do under TC(W) No. 8/2025 Annex A: every G.F. 527 field, retrieval from the Site Diary, workflow, statistics and SpatialSense.
- RISCThe RISC form in the DWSS under TC(W) No. 8/2025 Annex A 7.5: the form it digitises, fields, workflow and sign-off, dashboard, and how SpatialSense delivers it.
- Site DiaryWhat the DWSS Site Diary module must do under TC(W) No. 8/2025 Annex A 7.5: G.F. 536, Site Record Book, content, workflow, statistics, and how SpatialSense delivers it.
- Site safety inspectionWhat the DWSS Site Safety Inspection Records module must do under TC(W) No. 8/2025 Annex A: safety walks, performance records, workflow, statistics and SpatialSense.
- Smart construction managementSmart construction management in the DWSS under TC(W) No. 8/2025: the SCM hub, alerts, dashboards, iCWP data within 24 hours, the AI tool, and how SpatialSense meets it.
- TC(W) No. 8/2025DEVB TC(W) No. 8/2025 in plain terms. Who must adopt the DWSS, the HK$30 million threshold, 1 April 2026, changes from TC(W) No. 2/2023, cost ceiling, EDMS and audit.
- Tender checklistA clause-by-clause checklist of DEVB TC(W) No. 8/2025 Annex A for DWSS tenders: proposal contents, access, security, backup, availability, timeline, handover and AI.
See NEC workflows in SpatialSense
Send us the contract form and options. We will walk through compensation events, early warnings and Health Check data.
