How to choose a DWSS

Choose a DWSS by testing it against Annex A of DEVB TC(W) No. 8/2025, because the circular sets requirements and does not name products. Ask each vendor to show all six mandatory modules, Smart Document Management, the iCWP data flow, security and backup, AI and the delivery timeline. This guide lists the tests and how Kodifly answers each.

Last updated

Start from the circular, not the brochure

The circular lays down what a DWSS must do. It does not approve products. The employer's representative reviews the contractor's proposal against the contract specification before accepting it (paragraph 13), and the DWSS is a standard item in technical audits (paragraph 16). So the practical test is simple. Can the vendor show each Annex A requirement working, before the contract starts?

The table gives nine criteria. Ask for a live demonstration of each, not a slide. Annex A 3.1.1 expects a live demonstration within one month of commencement anyway.

Nine evaluation criteria

CriterionAnnex A testAsk the vendorHow Kodifly answers
Six modules1.2.1, 7.5Show RISC, Site Diary, Safety, Cleansing, Labour Return and Contract Management liveAll six are live in SpatialSense
Document management9, paragraph 11Does it replace a separate EDMS, including external reviewers by email?Smart Document Management is part of SpatialSense
iCWP data1.7.2, 11.1.5Which DSR version? Daily upload? API documents?Built to Annex A, with the iCWP link set up in the project
Mobile access1.6.3, 5.7.3Is the app native on iOS and Android? Does it work offline?Web, iOS and Android apps
Security and backup4.1, 4.2, 2.4Show auditor reports, a restore test and the recovery pointSecurity, backup and audit trail built to Annex A
AI1.5.1, 1.5.2Which AI features? How are they documented under our privacy policy?AI built in, with reports drafted by SpatialSense AI and reviewed by your team
Timeline3.1Demo in one month, proposal in eight weeks, live in three?The same timeline
Handover11.2Show a sample handover package: SQLite files, PDFs and registerBuilt to 11.2 and the handover duties in paragraph 15
Site data8, 1.3Who supplies and installs the devices that feed the hub?Kodifly delivers software, devices and installation as one project

Red flags

Signs that a proposal may not meet the circular.

  1. Modules and documents

    • A separate EDMS offered as an add-on, when paragraph 11 says Smart Document Management replaces it
    • Fewer than six modules, or modules shown only as mock-ups
    • No answer on NEC Health Check data for NEC contracts (7.5.1)
  2. Data and integration

    • No mention of the Data Standardisation Report or its version
    • Data released only on request, with no API (1.7.2, 11.1.1)
    • No handover plan for databases, PDFs and register (11.2)
  3. Security and AI

    • No independent auditor reports for cloud hosting (2.3.2)
    • Backups never restored in a test (4.2.6)
    • AI features that are not documented in the proposal (1.5.2)

One supplier for the whole requirement

Kodifly delivers the software, devices and installation as one project.

One project

  • SpatialSense DWSS

  • 360 helmet camera

  • Fixed-route drone LiDAR

  • ScanStation K4DL-1000

  • AI built in

Choosing a DWSS, answered

Is there an approved list of DWSS products?

The circular sets requirements in Annex A and does not name products. The employer's representative reviews each contractor's DWSS proposal against the contract specification (paragraph 13).

What should I ask in a DWSS demonstration?

Ask to see all six mandatory modules working with their Annex A fields (7.5), the Smart Document Management reviewer flow (9.7), the iCWP dataset (1.7.2) and the handover package (11.2).

Does it matter where the DWSS is hosted?

Annex A allows a site office, an external data centre or the cloud (2.1.1). Cloud hosting needs up-to-date independent auditor reports (2.3.2) and a daily local copy if it is software as a service (4.2.7).

How long should it take to go live?

Annex A 3.1 asks for a live demonstration within one month, a proposal within eight weeks and commissioning within three months, or as agreed with the employer's representative.

Who owns the data?

All data in the DWSS becomes the property of the HKSAR Government, and the DWSS is licensed under "HKSAR Government" (11.3.1, 11.3.3). Ask how a vendor's terms fit that.

Does the cheapest option comply?

Cost is not a compliance test. The estimated cost would normally not exceed HK$1.5 million or 1% of the pre-tender estimate, whichever is higher, with a cap of HK$10 million (paragraph 12). Compare proposals against Annex A first.

More DWSS guides

  • Cleansing inspectionWhat the DWSS Cleansing Inspection Checklists module must do under TC(W) No. 8/2025 Annex A: daily and weekly checklists, records, workflow, statistics and SpatialSense.
  • Contract managementWhat the DWSS Contract Management module must do under TC(W) No. 8/2025 Annex A: compensation events, early warnings, payment, programme, NEC Health Check data.
  • GlossaryA sourced glossary of DWSS terms in Hong Kong public works: DWSS, iCWP, DSR, RISC, SCM, SDM, EDMS, SSSS or 4S, CSP, NEC and PTE, with the circular paragraph for each.
  • iCWP data standardHow a DWSS feeds DEVB's iCWP under TC(W) No. 8/2025. The data standardisation rule, the 24-hour API clause, what data flows and how SpatialSense meets it.
  • Labour ReturnWhat the DWSS Labour Return module must do under TC(W) No. 8/2025 Annex A: every G.F. 527 field, retrieval from the Site Diary, workflow, statistics and SpatialSense.
  • RISCThe RISC form in the DWSS under TC(W) No. 8/2025 Annex A 7.5: the form it digitises, fields, workflow and sign-off, dashboard, and how SpatialSense delivers it.
  • Site DiaryWhat the DWSS Site Diary module must do under TC(W) No. 8/2025 Annex A 7.5: G.F. 536, Site Record Book, content, workflow, statistics, and how SpatialSense delivers it.
  • Site safety inspectionWhat the DWSS Site Safety Inspection Records module must do under TC(W) No. 8/2025 Annex A: safety walks, performance records, workflow, statistics and SpatialSense.
  • Smart construction managementSmart construction management in the DWSS under TC(W) No. 8/2025: the SCM hub, alerts, dashboards, iCWP data within 24 hours, the AI tool, and how SpatialSense meets it.
  • TC(W) No. 8/2025DEVB TC(W) No. 8/2025 in plain terms. Who must adopt the DWSS, the HK$30 million threshold, 1 April 2026, changes from TC(W) No. 2/2023, cost ceiling, EDMS and audit.
  • Tender checklistA clause-by-clause checklist of DEVB TC(W) No. 8/2025 Annex A for DWSS tenders: proposal contents, access, security, backup, availability, timeline, handover and AI.

Put SpatialSense through the nine tests

Send us your contract and tender date. We will run the demonstration against your Annex A clauses.