DEVB TC(W) No. 1/2026, Annex A

Co-supervision Platform functions, and the site data behind each one

Annex A of DEVB TC(W) No. 1/2026 lists four technologies behind SmartEye, the Co-supervision Platform, and nine functions, from the time series point cloud viewer to the AI chatbot. Every function runs on site data. Kodifly supplies that data with fixed-point and fixed-route 4D LiDAR, cameras, sensors and edge units, installed as one project.

Last updated

What the platform does, in one paragraph

SmartEye is the Co-supervision Platform (CSP) that DEVB developed in-house (paragraph 6). It gives works departments, consultants and contractors one place to check workmanship, productivity, positions and dimensions off site, round the clock (paragraph 7). Annex A, paragraph 1, says pilots have run in selected public works projects since late 2024.

Annex A explains the platform in three layers. Paragraph 2 names four technologies, 4D LiDAR, edge computing, 5G fusion bonding, and Generative AI with a Large Language Model. Paragraph 3 lists the other devices it can read, cameras, sensing equipment and works-specific devices. Paragraph 5 lists nine functions for quality checks, site measurements, construction monitoring and contract administration.

A dashboard function is only as good as the data reaching it. A volume figure needs a dimensionally sound point cloud. A rebar check needs a view that sees the bars before the concrete goes in. This guide takes each item in Annex A, states the site data it depends on, and shows how Kodifly supplies it.

The four technologies in Annex A, paragraph 2

What each technology does in the platform, and what has to be on site for it to work.

TechnologyWhat Annex A saysWhat the site must supplyHow Kodifly supplies it
4D LiDAR, Video of Point CloudCombines time-series imaging with LiDAR point clouds for dimensional and positional information. Produced by a fixed-point or fixed-route approach (para 2(i)).Repeated scans of the same works area, so changes can be seen over time.ScanStation K4DL-1000 on poles or tower cranes, plus fixed-route drone LiDAR for areas a fixed unit cannot see.
Edge computingOptimises point cloud size, adds colour and georeferencing, and gives zero-lux vision for round-the-clock monitoring (para 2(ii)).Processing at the device, close to the sensor, before the data leaves site.Kodifly edge units installed with the LiDAR. ScanStation outputs real-time colourised point clouds with centimetre-level georeferencing.
5G fusion bondingCombines bandwidth from several mobile operators to raise uplink bandwidth up to about three times (para 2(iii)).A stable uplink from each capture point to the platform.Kodifly plans the uplink for every capture point as part of the installation.
Generative AI and LLMTurns site data into actionable intelligence through an AI-driven interactive dashboard (para 2(iv)).Dated, located, structured records the model can read and compare.Every scan and reading is dated and georeferenced. SpatialSense drafts site reports from the same record.

The nine functions in Annex A, paragraph 5

The functions DEVB has developed so far. New modules, such as NEC contract administration, are being added in stages.

FunctionData it needs from siteHow Kodifly supplies it
(i) Time series point cloud viewer for 4D LiDAR videosPoint clouds of the same area captured again and again, aligned to one coordinate frame.Fixed-point ScanStation watching one area over time, with fixed-route drone passes added on the same frame.
(ii) Dimension and volume measurementGeoreferenced point clouds with known accuracy over the stockpile, excavation or structure.ScanStation range accuracy of ±2 cm (1σ), with absolute accuracy of 8 cm or better as RMSE against at least 10 RTK checkpoints, as the CSP Particular Specification A1 1.1(f) requires.
(iii) Slope angles and ground profile measurementRepeated scans of the slope or formation surface from a stable viewpoint.Pole-mounted units facing the slope, with drone routes over wider formation areas.
(iv) Check on reinforcement bar fixingA clear, dense view of the bars before concreting.Units placed on tower cranes or poles with a line of sight to the deck, timed to the pour programme.
(v) Productivity check for MiC installationA time series over the lifting and placing zone for each module.Crane-mounted and pole-mounted units covering the installation area.
(vi) Efficiency check for tower crane operationContinuous capture of the crane, its loads and the set-down areas.Units on the crane or on poles with a view of its working radius.
(vii) Alerts systemContinuous data from LiDAR, cameras and sensors, with thresholds set for the works.Round-the-clock capture, AI cameras and IoT sensors, delivered on the same platform.
(viii) Site report generationDated records of progress, measurements and events.Dated scans and readings, with SpatialSense drafting site reports.
(ix) AI chatbotStructured site data tagged by date and location.Every capture is stored with its date and position, so questions can be answered from the record.

Project-specific additions to the nine functions

Some contracts add checks of their own on top of the nine Annex A functions, most often on slopes and retaining structures. These are additions written into the contract, not functions listed in the circular.

AdditionData it needs from siteHow Kodifly supplies it
Soil nail head monitoringRepeated scans of the slope face, with each nail head located and compared with its first position.Fixed-point ScanStation facing the slope, georeferenced in the HK1980 Grid, so each head's displacement is logged by date.
Rock anchor monitoringA stable time series over the anchor heads and the rock face around them.The same fixed-point time series, with each anchor head tracked against its baseline and alerts raised on movement.
Retaining wall rebar checkA dense view of the wall reinforcement before concreting, to compare spacing with the drawing.Pole-mounted or handheld LiDAR scans of the cage, timed to the pour, with spacing measured from the point cloud.

Optional items in the CSP Particular Specification

The specification lists optional items a contract may add to the main appliances (section 3.4). Two are often asked for.

Optional itemWhat the specification requiresHow Kodifly supplies it
Video analyticsScenario-based AI for unsafe acts, object counting and tracking, with alerts, snapshots and video clips sent to the dashboard (A1 4.1). Results carry date, time, alert type, equipment, snapshot and video link (A2 1.11). Contract specifications commonly ask for counting plant and workers and tracking materials in real time.AI cameras and the fixed-point camera feed, counting plant and workers and sending the results to the SmartEye dashboard.
LoRaWAN gateway and LoRa IoT sensorsGateway compatible with EMSD's Government-wide IoT Network (GWIN), 920 to 925 MHz, HKCA 1078, LoRaWAN v1.0.2 or later, daily heartbeat, IP66 (A1 4.2). Vibration, tilt, location, temperature and humidity, and PM2.5 and PM10 sensors, registered on GWIN with OTAA and hourly updates (A1 4.3). Data passed to the GWIN network server over TLS (A2 1.1 to 1.7).Gateways and sensors registered on GWIN, with readings and connection alerts shown on the SmartEye dashboard.

The devices in Annex A, paragraph 3, delivered.

Apart from 4D LiDAR, the platform reads data from cameras, sensors and works-specific devices. The list is not exhaustive.

All supplied, installed and supported by Kodifly

  • Fixed-point ScanStation K4DL-1000

  • Fixed-route drone LiDAR

  • AI cameras

  • Body-worn cameras

  • Temperature, humidity and vibration sensors

  • LoRaWAN gateway and LoRa IoT sensors on GWIN

  • Video analytics counting plant and workers

  • Edge units at each capture point

  • Site report drafting in SpatialSense

  • Link to the DWSS hub

Readings, levels and alerts in one view.

Each monitored point shows its latest displacement and its status against alert, alarm and action levels. The trend shows how it got there.

Co-supervision Platform functions, answered

How many functions does the Co-supervision Platform have?

Annex A, paragraph 5, of DEVB TC(W) No. 1/2026 lists nine functions, a time series point cloud viewer, dimension and volume measurement, slope angle and ground profile measurement, reinforcement bar fixing check, MiC installation productivity check, tower crane efficiency check, an alerts system, site report generation and an AI chatbot. New functions, such as NEC contract administration modules, are being introduced in stages.

What is the Video of Point Cloud?

It is SmartEye's 4D LiDAR output, combining time-series imaging with LiDAR point clouds to give dimensional and positional information over time (Annex A, paragraph 2(i)). It is produced by LiDAR on fixed poles, tower cranes or non-movable objects, or by small unmanned aircraft or robots on a fixed route. Kodifly supplies both, with ScanStation K4DL-1000 and fixed-route drone LiDAR.

What does edge computing do in SmartEye?

Annex A, paragraph 2(ii), says edge computing optimises the size of point cloud images, adds colour and georeferencing, and provides zero-lux vision for round-the-clock monitoring. Kodifly installs edge units with its LiDAR, and ScanStation outputs real-time colourised point clouds with centimetre-level georeferencing.

What is 5G fusion bonding?

It combines data bandwidth from multiple mobile operators into one large channel, increasing uplink bandwidth up to about three times (Annex A, paragraph 2(iii)). It matters because point clouds are large and must reach the platform from site continuously.

Which sensors can feed the platform besides LiDAR?

Annex A, paragraph 3, lists AI cameras and body-worn cameras, IoT sensors for temperature, humidity, vibration and other environmental parameters, and works-specific devices such as thermal sensors, fibre optic sensors and handheld laser scanners. The list is not exhaustive. Kodifly supplies and installs these alongside the LiDAR.

Does the platform connect to the DWSS?

Yes. The CSP should support data connection with the Smart Construction Management hub of the DWSS through an API or other means (Annex A, paragraph 4, and paragraph 8 of the circular). DWSS requirements on acceptance, handover, technical audit and the iCWP interface also apply to the CSP (paragraph 16).

Can a contract add functions beyond the nine in Annex A?

Yes. Some contracts add project-specific checks, such as soil nail head and rock anchor monitoring on slopes and rebar checks on retaining walls. They are additions to the nine Annex A functions, written into the contract. Kodifly supplies them from the same fixed-point and handheld LiDAR record.

Which optional items can a CSP contract include?

Section 3.4 of the CSP Particular Specification lists video analytics, a LoRaWAN gateway, LoRa IoT sensors, an RTK-GNSS receiver, a thermal infrared camera and body-worn video cameras. LoRa sensors connect through EMSD's Government-wide IoT Network, GWIN (Appendix A2, 1.1 to 1.7). Kodifly supplies all of them.

Who developed SmartEye?

DEVB developed SmartEye in-house to establish the Co-supervision Platform (paragraph 6 and Annex A, paragraph 1). Kodifly supplies the site capture, hardware, software and services the platform uses on a contract.

More Co-supervision Platform guides

  • DeploymentsKodifly has fitted around 20 Hong Kong public works contracts with LiDAR, cameras and edge units for the Co-supervision Platform. Departments, scope and how we deploy.
  • Fixed-point vs fixed-routeTC(W) No. 1/2026 allows fixed-point LiDAR on poles or tower cranes and fixed-route LiDAR on drones or robots. When to use each, blind spots, and how Kodifly plans both.
  • Particular SpecificationWhat the CSP Particular Specification under DEVB TC(W) No. 1/2026 requires, clause by clause, from LiDAR and edge hardware to accuracy, testing and security.
  • Scope and vettingTC(W) No. 1/2026 requires the Co-supervision Platform for capital works above HK$400 million tendered from 1 April 2026. Scope, vetting, exemptions and the DWSS link.
  • SmartEye compatible captureWhat capture data SmartEye, DEVB's Co-supervision Platform, needs under TC(W) No. 1/2026, and how Kodifly's LiDAR, cameras, sensors and edge units deliver it.

Plan the capture for each function

Tell us the site, works type and the functions in your CSP scope. We will plan the fixed-point and fixed-route capture they need.