Public works contract specification

BWVC contract specification: what Hong Kong public works contracts now require

DEVB publishes no central body-worn video camera (BWVC) specification, but recent Hong Kong public works contract specifications now set one. The camera weighs 400 g or less, holds at least 256GB, records 9 hours of 1080p at 30 fps with audio on one battery, and its footage is kept at least 7 days and deleted 7 days after completion. Kodifly's kit, an Insta360 X6 on the safety helmet with a 256GB card and a USB-C power pack, and SpatialSense meet every requirement.

Last updated

Contracts now set the specification

DEVB has required body-worn video cameras on public works site inspections since June 2026 (LC Paper No. CB(1)749/2026(02), paragraph 40). Its public papers state the requirement and its four purposes. They publish no central camera specification.

Recent Hong Kong public works contract specifications now set one. They fix the weight, storage, battery, video, audio, mounting, notice, retention, access and deletion, and they add an implementation plan and support times. This page follows those current contract requirements. Read your own clause against the table, because the contract you sign governs.

The requirements, and how Kodifly meets them

What recent public works contract specifications require, item by item.

RequirementWhat current contracts setKodifly
Implementation planWithin 14 days of the starting date: scenarios to record, areas where recording is restricted, staff who wear a camera, staff who may access footage, a designated person for personal data, and security controls. Reviewed monthlyKodifly drafts it
Number of setsAt least 6 sets for the Client and the Project Manager, plus enough for foremen, Safety Officers and Safety Supervisors. Worn during all site inspectionsMeets
DeliveryCameras and accessories within 14 days of acceptance of the first implementation planMeets
SupportMaintenance, repair, technical support or training within 2 days of request. A replacement for the period of any breakdownMeets
Spare batteriesWithin 7 days of request, for cameras with removable batteriesMeets
Weight400 g or lessMeets
StorageAt least 256GB, built in or on a V10 or higher microSD card, holding at least 7 days of 1080p30 video and audioMeets
Site conditionsWorks in aggressive site environments such as heavy dust and gas hazardMeets
BatteryAt least 9 hours of continuous 1080p30 recording on one fully charged batteryMeets
Video1080p at 30 fps or higher, with audio. Date and time watermark. Low-light recordingMeets
AudioBuilt-in microphones and built-in speakersMeets
MountingAdjustable chest or shoulder straps, or equivalent, for hands-free recording. A camera that integrates with a smart safety helmet may be proposedMeets
AccessoriesBatteries and chargers from the camera's authorised dealerMeets
Privacy lawThe PDPO (Cap. 486) and PCPD's Privacy Guidelines, Monitoring and Personal Data Privacy at WorkMeets
NoticeA conspicuous bilingual notice, Video & Audio Recording In Progress 錄影及錄音現正進行中, on or alongside the cameraMeets
Retention and accessStored securely for at least 7 days. Available to designated Client and Project Manager staff within 24 hours of requestMeets
People and briefingAn access list and a named designated person in the plan. Everyone on site is told at induction that footage may go to the law enforcement authority, the Client and the Project ManagerMeets
Training useNo disclosure to unrelated parties without permission. Personal data blurred before any training useMeets
Security and trainingControls for confidentiality, integrity and availability, reviewed regularly. Training for camera users and staff with accessMeets
DeletionAll footage deleted 7 days after completion of the whole of the worksMeets

How the kit meets the camera items

Kodifly's kit is an Insta360 X6 on the safety helmet. The camera figures are Insta360's own.

ItemWhat current contracts setThe Kodifly kit
Weight400 g or lessInsta360 X6, 196 g
StorageAt least 256GB, built in or on a V10 or higher microSD cardA 256GB microSD card, V30, in each camera. The X6 also has 64GB built in
BatteryAt least 9 hours of continuous 1080p30 recordingThe X6's own battery runs about 200 minutes at most. A USB-C power pack in the kit covers the 9 hours
Video1080p at 30 fps or higher, with audio8K 360 video with audio, above 1080p30
Site conditionsHeavy dust and other aggressive site environmentsDust-tight and waterproof, rated IP6X and IPX8
MountingChest or shoulder straps, or a camera that integrates with a safety helmetHelmet mount, with a chest or shoulder strap option
AccessoriesBatteries and chargers from the authorised dealerBatteries and a charger in each kit. Kodifly sells the X6
NoticeBilingual notice on or alongside the cameraSupplied for the helmet

Insta360's X6 specification: 196 g, a 2600 mAh battery with about 200 minutes at 6K 24 fps in Endurance Mode, 64GB built in, microSD up to 1TB, IP6X and IPX8. Other cameras SpatialSense works with (Insta360 X5 and X4, DJI Osmo 360) can be proposed where a contract allows.

The clause from award to deletion

  1. Within 14 days

    Implementation plan

    Kodifly drafts the plan from the starting date, with the wearers, access list and designated person.

  2. Within 14 days

    Cameras delivered

    Cameras, batteries, chargers and notices arrive within 14 days of the plan's acceptance.

  3. Each inspection

    Worn at every inspection

    Video and audio at 1080p30, with the date and time watermark.

  4. Monthly

    Plan updated

    The plan follows site progress and the prevailing site condition.

  5. Within 24 hours

    Footage on request

    Designated Client and Project Manager staff get the footage they ask for.

  6. 7 days after completion

    Footage deleted

    All video and audio is deleted and the cameras leave the site.

What Kodifly delivers against the clause

  • The camera

    An Insta360 X6 on the safety helmet, as current contracts allow. It records hands-free with the whole scene in view, and the SpatialSense app sends each walk to the project.

  • The record

    SpatialSense keeps the footage behind the project login, dated and placed on the floor plan, with an audit trail of who opens it.

  • The paperwork

    Kodifly drafts the implementation plan, the monthly update, the bilingual notice and the induction briefing text.

Contract specification questions

Does DEVB publish a body-worn camera specification?

Not centrally. LC Paper CB(1)749/2026(02), paragraph 40, states the requirement and its purposes. Recent Hong Kong public works contract specifications now set the figures, and this page follows those current contract requirements.

What weight, storage and battery do current contracts require?

400 g or less, at least 256GB of storage on the camera or a V10 or higher microSD card, enough for 7 days of 1080p30 video and audio, and 9 hours of continuous 1080p30 recording on one battery. Kodifly's kit meets each, with an Insta360 X6 at 196 g, a 256GB card, and a USB-C power pack for the 9 hours.

Must the camera record audio?

Yes. Current contracts require 1080p at 30 fps or higher with audio, built-in microphones and built-in speakers. The bilingual notice Video & Audio Recording In Progress 錄影及錄音現正進行中 tells people that sound is recorded too.

Can a helmet camera meet a BWVC clause?

Yes. Current contracts ask for chest or shoulder straps or an equivalent hands-free mount, and allow a camera that integrates with a smart safety helmet if it meets the rest of the clause. Kodifly's kit, an Insta360 X6 on the helmet, is that option. The mount goes in the implementation plan for the Project Manager's acceptance, and a chest or shoulder strap is available.

How long must footage be kept, and who can see it?

At least 7 days, stored securely. Designated staff of the Client and the Project Manager must receive footage within 24 hours of a request. Only the people on the access list in the implementation plan may open it.

When is the footage deleted?

7 days after completion of the whole of the works, all video and audio footage is deleted. The cameras then become the contractor's property and leave the site.

Which privacy rules does the clause name?

The Personal Data (Privacy) Ordinance (Cap. 486) and PCPD's Privacy Guidelines, Monitoring and Personal Data Privacy at Work. The footage and privacy guide applies them to site inspections.

How many cameras does a contract need?

At least 6 sets for the Client and the Project Manager, plus enough for the contractor's foremen or equivalent, Safety Officers and Safety Supervisors. The allocation goes in the implementation plan.

More body-worn camera guides

  • Footage and privacyBody-worn camera footage of identifiable people is personal data under the PDPO. PCPD guidance applied to site footage, with a policy checklist.
  • Inspection workflowA step-by-step site inspection video record workflow, from start of shift to retention. Footage is dated, placed on the floor plan and linked to DWSS records.
  • Requirement explainedDEVB has required body-worn video cameras on public works site inspections since June 2026. Who wears them, from when, why, and what your contract adds.

Get a BWVC plan for your contract

Tell us the contract and its start date. We will draft the implementation plan and show the camera against each requirement.