LC Paper No. CB(1)1487/2026(04), Panel on Development, 24 November 2026
Proposed Buildings Ordinance amendments: what changes for contractors, TCPs and site records
The Development Bureau has proposed amendments to Hong Kong's Buildings Ordinance (Cap. 123). They would raise the maximum fine for material deviation from approved plans from HK$1 million to HK$3 million, define the duties of technically competent persons (TCPs) in the Ordinance, require a CIC-registered TCP in every site supervision plan, and extend the period for keeping supervision records from 12 months to six years. The proposals went to the Legislative Council Panel on Development on 24 November 2026. The Government plans to introduce the bill in January 2027 and to bring it into force by mid-2027.
Last updated
These are proposals the Development Bureau put to the Legislative Council Panel on Development on 24 November 2026 for discussion. The Government will finalise them after hearing Members and the industry. The figures below are from the Administration's paper and may change in the bill.
What was proposed
The Development Bureau and the Buildings Department (BD) began reviewing the Buildings Ordinance about two years ago. A first set of proposals went to the Panel on Development in December 2024 and to a two-month public consultation in early 2025. After the Wang Fuk Court fire the review was widened to cover large-scale building repair. The latest proposals cover five areas: large-scale building repair, building works safety, unauthorised building works, compliance with statutory orders, and other amendments (paper, paragraph 3).
For people who build, the part that matters most is Part II, enhancing building works safety. It defines the duties of key site personnel, gives BD stronger powers to collect evidence, raises penalties and tightens registration and discipline (paragraphs 9 to 14).
The proposals are separate from BD's planned photo and video record of rebar before concreting. That is not in the paper. BD plans to bring it in by January 2027, months before the amended Ordinance could take effect. Both point the same way. Records of what was built will be asked for, by BD, and over a longer period.
Penalties, current and proposed
The maximum penalties in the paper for the offences that most affect building works.
| Offence | Current maximum | Proposed maximum | Paper |
|---|---|---|---|
| Material deviation from approved plans, prescribed plans or site supervision plans; defective or non-standard materials; misrepresenting a material fact (section 40(2A)) | HK$1,000,000 and 3 years | HK$3,000,000 and 3 years | Para 13(a) |
| Works carried out in a way that causes or is likely to cause injury or damage (section 40(2B)), summary conviction | HK$1,000,000 and 3 years | HK$3,000,000 and 3 years | Para 13(b)(i) |
| The same offence, on indictment (new) | None | HK$10,000,000 and 5 years | Para 13(b)(ii) |
| Failing to provide records as required by BD (new) | No offence | HK$100,000 | Para 12(a) |
| Refusing an interview or refusing to submit works supervision documents (new) | No offence | HK$100,000 | Para 12(b) |
| Disciplinary fine on a registered contractor or building professional | HK$250,000 | HK$1,500,000 | Para 14(d)(iv) |
Source: LC Paper No. CB(1)1487/2026(04). The 40(2B) indictable offence follows the Occupational Safety and Health Ordinance.
Technically competent persons move into the Ordinance
Today the Ordinance sets out duties only for registered building professionals and registered contractors. It says nothing about the people who act for a contractor, the authorized signatory and the technical director, or about the technically competent persons "responsible for supervising details of works and keeping works records". The proposal defines their duties in the Ordinance, with details in a Technical Memorandum, so that they carry legal liability for building works (paragraph 11(a)).
TCPs do not have to be registered now. The Construction Industry Council (CIC) runs a voluntary register. Under the proposal, a site supervision plan must confirm that a TCP registered with the CIC has been appointed (paragraph 11(b)).
This is the same group the rebar measure relies on. BD's planned rule has TCPs under the registered structural engineer verify every pre-pour rebar record. Once the bill passes, verifying and keeping those records becomes a duty written into the Ordinance.
Records kept for six years, and handed over on request
The Ordinance already requires registered contractors to keep supervision records and documents of building works for at least 12 months. Because some contraventions are found later and need older records, the paper extends the period to six years, and registered building professionals must keep the records as well (paragraph 12(a)).
The Ordinance sets no penalty today for failing to keep records. The proposal makes failing to provide records as BD requires a new offence, with a maximum fine of HK$100,000. BD would also gain powers to request interviews, search and seize documents under warrant, and refusing to submit works supervision documents would be a new offence (paragraph 12(b)).
Six years is longer than most projects. A record taken on a phone and shared in a chat group may be gone when BD asks for it years later. Records that can be found by element and date, and handed over as a set, are what the proposal expects.
Registration and discipline
| Change | What the paper proposes | Paper |
|---|---|---|
| Contractor renewal after a fatal incident or a 40(2A) or 40(2B) conviction | BD may attach conditions such as site supervision or safety management, or bar the authorized signatory or technical director involved for 12 months. Registration stays at three years | Para 14(a) |
| Contractor renewal with no such record | Registration period extended from three to five years | Para 14(a) |
| Bribery or bid-rigging | Removal from the register without disciplinary proceedings, and no re-entry for three years | Para 14(b) |
| Building professionals' renewal | BD may require an interview and will consider past performance, convictions and disciplinary records | Para 14(c) |
| Disciplinary hearings | Panel for building professionals grows from 25 to 40 members; contractors' boards no longer need every professional stream; more cases started on performance records; more than one sanction per allegation | Para 14(d) |
Source: LC Paper No. CB(1)1487/2026(04), paragraph 14.
Also in the paper
Large-scale building repair, mostly Class II minor works today, would become a new category of works. It would need a permit, supervision by an authorized person and a registered general building contractor or Class I minor works contractor. Starting without a permit would carry a maximum fine of HK$2 million and two years' imprisonment (paragraphs 5 and 6).
Electronic submission of building plans would become mandatory, at the earliest in the second half of 2027. The Government's target is to mandate BIM for statutory plan submissions on large private developments, over 25,000 square metres of gross floor area, in 2029 (paragraphs 25 and 26).
What contractors and TCPs can do now
Name your TCPs and check their CIC registration
The site supervision plan will have to confirm a CIC-registered TCP. Know who they are on each site before the bill arrives.
Treat every supervision record as a six-year record
Keep inspection records where they can still be found years from now, not on personal phones or in chat groups.
Make records findable by element and date
Tie each record to the level, grid and element on the approved plans, with the date, time and person who took it.
Be able to hand over a set on request
Failing to provide records to BD would be an offence. Practise exporting the records for one pour as a single set.
Start with the rebar record
BD's pre-pour rebar record starts by January 2027, before the bill. It is the first record most sites will have to submit.
How Kodifly delivers it
A record for every element
Photos or a 360 walk, placed on the plan by level and grid with date, time and capture ID.
The TCP's check kept with it
The inspection request carries who submitted, who inspected and who approved, and when.
Buildings Ordinance amendment questions
What are the proposed Buildings Ordinance amendments?
Proposals by the Development Bureau to amend the Buildings Ordinance (Cap. 123) in five areas: large-scale building repair, building works safety, unauthorised building works, compliance with statutory orders, and other amendments. They went to the Legislative Council Panel on Development on 24 November 2026 (LC Paper No. CB(1)1487/2026(04)).
When will the amendments take effect?
The Government plans to introduce the bill into the Legislative Council in January 2027 and aims to complete the legislative process and bring the amended Ordinance into force by mid-2027. The Secretary for Development may set separate start dates for individual provisions (paper, paragraph 29 and footnote 15).
What is the new maximum fine for deviating from approved plans?
HK$3 million, up from HK$1 million, with imprisonment remaining at three years. The offence under section 40(2A) also covers defective materials, materials that breach prescribed standards, deviation from prescribed plans or site supervision plans, and misrepresenting a material fact (paragraph 13(a)).
Will technically competent persons have to be registered?
When a site supervision plan is prepared, it must confirm that a technically competent person registered with the Construction Industry Council has been appointed. The Ordinance will also define TCPs' duties, with details in a Technical Memorandum (paragraph 11).
How long must site supervision records be kept?
Six years, under the proposal, instead of at least 12 months today. Registered building professionals must keep the records too, and failing to provide records as BD requires becomes an offence with a maximum fine of HK$100,000 (paragraph 12(a)).
Does the bill include the rebar photo and video record?
No. The pre-pour rebar record is a Buildings Department measure announced on 11 November 2026 and planned for January 2027 or earlier, before the amended Ordinance could take effect. The paper does not mention it. The proposals raise the penalties and record duties around it.
Do registered contractors get anything in return?
Yes. Contractors not involved in a fatal site incident and not convicted under section 40(2A) or 40(2B) during the registration period would renew for five years instead of three (paragraph 14(a)).
Do the amendments apply to public works?
The Buildings Ordinance governs private building works. Public works contracts follow the Development Bureau's own rules, such as the Digital Works Supervision System and body-worn cameras during inspections. The comparison guide sets the record rules side by side.
Related guides
More rebar records guides
- Requirement explainedBD plans to require photo or video records of rebar before concreting in Hong Kong, by January 2027. Who records, who verifies, what goes to BD and what is still open.
- Public and private worksDoes DWSS apply to private projects in Hong Kong? DWSS and body-worn cameras are for public works. The Buildings Department's rebar record measure is separate.
- What to recordA checklist for the photo or video record of rebar before concreting. What each record should show so it can be verified against the approved plans and spot-checked.
Records that are still there in six years
Tell us the project and the pour programme. We will show the record on a site like yours, from the first photo to the set you hand to BD.