BCA Guidebook for Virtual TOP/CSC (360 Capture)

360 camera requirements for BCA virtual inspection: camera, platform and capture

BCA's Guidebook for Virtual TOP/CSC (360 Capture) sets the minimum for a virtual inspection in Singapore. The 360 camera supports at least 6K resolution, suits low light, has dual one-inch CMOS sensors, records 60 to 90 minutes on one battery and has six-axis stabilisation. The platform ties every capture to the approved building plan and lets BCA tag comments. SpatialSense meets the eight platform requirements and works with the Insta360 X4, X5 and X6 and the DJI Osmo 360.

Last updated

Resolution
At least 6K
Sensors
Dual one-inch CMOS, suitable for low light
Battery
60 to 90 minutes of continuous video capture
Stabilisation
Six-axis
Capture age
No more than three months before submission
BCA reply
Within three working days

What BCA requires of the 360 camera

BCA accepts a 360 capture in place of a physical TOP or CSC inspection, or as part of a hybrid one. Its Guidebook for Virtual TOP/CSC (360 Capture), published in November 2024, sets the minimum performance for the camera and the platform in section 4.1. A capture that falls short can be rejected, and the inspection goes back to a physical visit.

The camera requirement is short. It supports at least 6K resolution, is suitable for low-light conditions and carries dual one-inch CMOS sensors. Its battery supports at least 60 to 90 minutes of continuous video capture. It has six-axis stabilisation with image stabilisation for smooth video, and it works with Android and iOS devices.

BCA notes on its website that the guidebook may not reflect the latest requirements, so the Qualified Person confirms the current position with BCA at pre-consultation. Recent Singapore industrial contract specifications set their own minimum of a dual-lens 360 camera of at least 5.7K. An 8K camera clears both figures.

360 camera requirements, and the cameras SpatialSense works with

The camera items in section 4.1 of the guidebook, against the makers' published figures.

ItemWhat BCA's guidebook setsInsta360 X4 and X5Insta360 X6 and DJI Osmo 360
ResolutionAt least 6K8K 360 video8K 360 video
Sensors and low lightDual one-inch CMOS sensors, suitable for low-light conditionsTwo 1/2-inch sensors on the X4, two 1/1.28-inch on the X5Two 1/1.1-inch square sensors, which the makers describe as one-inch class
BatteryAt least 60 to 90 minutes of continuous video captureCheck the maker's figure at the resolution you capture, and carry sparesCheck the maker's figure at the resolution you capture, and carry spares
StabilisationSix-axis stabilisation with an image stabilisation algorithm for smooth videoBuilt-in gyro stabilisationBuilt-in gyro stabilisation
DevicesA high-quality 360 camera compatible with Android and iOS devicesAndroid and iOS appsAndroid and iOS apps

For a virtual TOP/CSC capture, choose the camera with the larger sensors, and confirm it with BCA at pre-consultation. Sensor sizes are from the makers' specifications, November 2026.

360 capture platform requirements

The eight platform items in section 4.1. BCA reviews the capture on the platform, so the platform matters as much as the camera.

ItemWhat BCA's guidebook setsSpatialSense
CamerasCaptures from most 360 camerasMeets
Capture modesContinuous capture for large areas, spot capture for small rooms such as a toilet unit, or a mix of bothMeets
Building planEvery photo and capture is tied to an uploaded building planMeets
EvidenceComments and extra photo evidence can be attached to the captureMeets
External accessExternal parties such as BCA inspectors can open the captureMeets
BCA commentsBCA inspectors can tag comments on the captureMeets
RectificationThe QP can attach photo or video evidence that each BCA comment is rectifiedMeets
ReportA report of all comments can be generated for the recordMeets

A spot capture must show all four sides of the room, the floor and the ceiling.

How the capture is carried out

The guidebook's capture practice in section 8.4, and its site preparation in section 5.

  1. Walking the building

    • Mount the camera on a hard hat, more than 20 cm above the head, or on a monopod or extension arm
    • Keep to the centre of the path, at least 2 metres from walls
    • Capture each area within a 5 to 10 metre radius
    • Pause 2 to 3 seconds at key areas
    • Walk at a normal pace. The platform maps about two images a second to the floor plan
  2. Light and weather

    • Add an LED light or spotlight in dim spaces, and use high exposure on a tripod in very dark ones
    • Slow down, or start a new session, when moving between bright and dark spaces
    • Do not capture in rain
    • Let the camera cool on hot days, and capture early or late
  3. Before and after the walk

    • All works complete and cleaned to a TOP-ready condition. Incomplete work seen in the capture is rejected
    • The latest approved building plan, with the primary accessibility route, loaded on the platform
    • Close-up measurement photos attached for each code item
    • A self-check that every location sits correctly on the plan

What must be captured, and when

Sections 2, 3, 7 and 11 of the guidebook.

RuleWhat BCA's guidebook sets
Non-typical areasAll of them, including landscape areas and common spaces inside the project boundary
Typical floorsAt least three in each building, one for every 10 floors, spread through the building
RoofsAny roof with maintenance access
External areasAll external areas drawn on the approved building plan
Age of the captureDone no more than three months before the capture is submitted
Phased submissionAllowed under the Virtual Inspection Plan, with all scans submitted inside three months
Pre-consultationBooked with BCA before the inspection booking. BCA may reject a request made less than three days before
BCA's reply to the planWithin three working days of receiving the Virtual Inspection Plan
BCA's comments on the captureWithin three working days of submission
Closure reportEvery non-compliance and observation with its rectification, submitted with the TOP/CSC documents

On the platform

BCA's comments, answered where they were raised.

BCA tags a non-compliance, an observation or a clarification in the capture. The Qualified Person replies in the same place with a photo of the rectification, and SpatialSense builds the closure report from those threads.

  • Every capture placed on the approved building plan
  • Close-up measurement photos attached to the position they prove
  • Closure report generated for the TOP/CSC submission

See virtual inspection

BCA's readiness check for virtual inspection solutions

Project teams may use any solution that meets BCA's virtual inspection requirements. BCA also publishes a self-assessment for solution providers. The provider scans a set route at BCA Academy and gives BCA the scan to assess.

The assessment has two categories. Digital Visualisation covers a cloud platform that shows a virtual digital twin of the site, lets users pin comments, attaches a photo of a sample measurement and generates an inspection report and a closure report. Digital Dimensional Measurement adds measurement inside the platform, with the stated accuracy of the camera or LiDAR scanner and the software together.

SpatialSense provides each of these functions, with measurement on the LiDAR point cloud for the second category.

360 camera questions for virtual inspection

What 360 camera does BCA require for a virtual TOP or CSC inspection?

BCA's Guidebook for Virtual TOP/CSC (360 Capture), section 4.1, sets a 360 camera that supports at least 6K resolution, suits low-light conditions, has dual one-inch CMOS sensors, records at least 60 to 90 minutes of continuous video on its battery and has six-axis stabilisation. It must work with Android and iOS devices.

Does BCA name an approved 360 camera model?

No. The guidebook sets minimum performance, not a brand or model. Any camera that meets section 4.1 can be used with a platform that meets the eight platform requirements.

Is a 5.7K 360 camera enough?

Not against the guidebook, which sets at least 6K. Some Singapore contract specifications set at least 5.7K as their own minimum. The Insta360 X4, X5 and X6 and the DJI Osmo 360 all record 8K, so they clear both.

What must the 360 capture platform do?

It ties every capture to the uploaded building plan, supports continuous and spot capture, gives BCA inspectors access to view and tag comments, lets the Qualified Person attach rectification evidence, and generates a report of all comments. SpatialSense does each of these.

How many floors must be captured?

All non-typical areas, at least three typical floors in each building at one for every 10 floors, any roof with maintenance access, and all external areas on the approved plan. The Qualified Person proposes the floors in the Virtual Inspection Plan and BCA confirms them.

How old can the 360 capture be?

The scans must be done no more than three months before the capture is submitted. A project that submits in phases keeps all its scan submissions inside three months.

How fast does BCA respond?

Within three working days of receiving the Virtual Inspection Plan, and within three working days of the capture being submitted for review.

Which projects can use a full virtual inspection?

The guidebook lists newly erected landed houses built by a developer for sale, newly erected industrial buildings with typical floor plans, parks and standalone structures, later partial TOP phases of HDB residential blocks, and A&A works in localised areas. Condominiums, hotel room floors, offices and institutional buildings of typical design can use a hybrid inspection. BCA decides case by case at pre-consultation.

Which 360 cameras work with SpatialSense?

The Insta360 X4, X5 and X6 and the DJI Osmo 360. All four record 8K 360 video, above BCA's 6K minimum. The Insta360 X6 and the DJI Osmo 360 carry the larger 1/1.1-inch sensors, the closest to the guidebook's one-inch figure, so they suit a virtual TOP/CSC capture best.

What does Kodifly provide?

SpatialSense, the platform BCA reviews the capture on, set up with the approved plans and the Virtual Inspection Plan. It works with the 360 camera your team already uses. Kodifly can also run the capture, and supports the Qualified Person until BCA closes the inspection.

Check your capture plan against the guidebook

Tell us the project and the TOP date. We will plan the floors, check your camera and show you the viewer BCA reviews.